Homeowners planning a garden light run or a garage sub-feed often ask the same question at the hardware store — can I just bury the indoor cable I already have? It looks similar to underground-rated cable, it is cheaper, and it saves a trip. The answer under the Ontario Electrical Safety Code is a firm no, and the reasons are more than paperwork. This guide walks GTA homeowners through whether you can bury indoor electrical wire underground, what happens if you do, and the alternatives that are code-compliant and safe.
Direct answer: burying NMD-90 (indoor Romex) directly in the ground violates the Ontario Electrical Safety Code and fails every ESA inspection. The jacket is not rated for wet or underground exposure, and moisture wicks along the conductor insulation, degrading it over years. Use NMWU (Non-Metallic Wet Underground) or install NMD-90 in listed underground conduit — not direct-buried.
The Electrical Safety Authority lists moisture-degraded underground cable among the residential incident causes tracked in the Ontario Electrical Safety Report. Slow-developing failures in buried cable are difficult to trace when they eventually cause a trip or an outdoor fixture failure.
Direct answer: PVC conduit around NMD-90 is often cheaper than direct-buried NMWU on shorter runs (under 15 metres) because NMD-90 is significantly cheaper per metre. The conduit adds material cost but the labour is comparable. For longer runs, direct-buried NMWU wins on total cost.
Conduit also gives you future flexibility — upgrading from 60 A to 100 A requires only pulling new cable, not re-trenching.
Our post on running power to a detached garage covers the full underground-run process.
Direct answer: low-voltage landscape lighting cable (12 V or 15 V) can be buried at 150-300 mm because it is low-voltage and the failure consequence is dim lights, not a shock. Standard 120 V branch circuits do not have a shallow-burial exception.
Our post on landscape lighting covers the low-voltage side.
In our experience diagnosing failed outdoor circuits across GTA back yards, the most common root cause we find is an indoor cable buried by a previous owner or handyman. It worked for 5 or 10 years, then gradually became unreliable. When we dig it up, the NMD-90 jacket is soft and cracked, the conductor insulation is powdery, and marrettes at any splice points are corroded green. The fix is always the same — replace with NMWU or install proper conduit. Customers often ask if we can splice a section — no, once NMD-90 has been buried for years, the whole run is compromised. Do it right the first time. Extra $50 in materials up front saves $500-1000 in retrenching later. Our post on wire types covers the material selection.